Enter demand, shifts, breaks and each station’s work content to get takt time, the Yamazumi chart, the bottleneck, the minimum number of operators and the annual cost of imbalance.
Pre-sizing and estimating tool: results do not replace design, calculations or reports signed by a licensed professional, nor verification against the applicable codes and standards.
Work content of each station with the takt line (red) and planned cycle time line (orange).
Ideal split of the same total work across the theoretical minimum number of operators.
Cash flow of the improvement: investment in year 0 and annual savings escalated at the rate entered, discounted at the MARR.
The report gathers this page's inputs, results, equations, assumptions and references, with fields for project, engineer and revision. In the print dialog, choose Save as PDF.
Divide available time by demand for the same period. Two 8-hour shifts with 60 minutes of breaks give 50,400 s; for 900 parts per day, takt is about 56 s.
Takt is the pace the customer asks for. Cycle time is the line’s real pace, set by the slowest station. The line meets demand only if cycle time is below takt.
Add the work content of all stations and divide by the planned cycle time, rounding up. With 290 s of work and a 52 s cycle, you need 6 operators.
Important notice: Indus Metrics tools produce estimates and pre-sizing results from the data you enter and from published engineering methods. They do not replace design, calculations or reports signed by a licensed professional engineer (PE), nor verification against the applicable codes, standards and regulations, such as OSHA rules and the ASME codes. Material and fuel properties vary: check manufacturer data or your own process analyses before deciding. By using this site you agree to the Terms of Use.