Enter inventories between steps, process times and throughput to see the real lead time, how much of it adds value and how much cash comes back by leaning the flow, without buying machines.
Pre-sizing and estimating tool: results do not replace design, calculations or reports signed by a licensed professional, nor verification against the applicable codes and standards.
Waiting before each step (days, from Little’s Law) and process time (barely visible at this scale).
Factory Physics best case and practical worst case; the dot is the current line and the diamond the proposal.
Cash flow of the improvement: investment in year 0 and annual savings escalated at the rate entered, discounted at the MARR.
The report gathers this page's inputs, results, equations, assumptions and references, with fields for project, engineer and revision. In the print dialog, choose Save as PDF.
That work-in-process equals throughput times lead time. With 5,900 parts in process and 900 leaving per day, lead time is about 6.6 days, even though each part is worked on for less than 4 minutes.
Yes, as long as throughput holds. If WIP drops below what is needed to feed the bottleneck (near critical WIP), throughput falls and the gain disappears.
Traditional plants are often below 5%. Well implemented cells and continuous flow reach 25% or more.
Important notice: Indus Metrics tools produce estimates and pre-sizing results from the data you enter and from published engineering methods. They do not replace design, calculations or reports signed by a licensed professional engineer (PE), nor verification against the applicable codes, standards and regulations, such as OSHA rules and the ASME codes. Material and fuel properties vary: check manufacturer data or your own process analyses before deciding. By using this site you agree to the Terms of Use.