Home / Electrical & motors

Motor overload and short-circuit protection

Enter the motor nameplate and starting data to get the overload setting, the trip class that fits, and the maximum fuse or breaker, starter and conductor sizes.

Pre-sizing and estimating tool: results do not replace design, calculations or reports signed by a licensed professional, nor verification against the applicable codes and standards.

Check
Motor
Starting
Short circuit

Setting and testing overloads, fuses and breakers is electrical work: qualified persons only, with the panel de-energized and locked out (NFPA 70E, OSHA 1910.147).

—Overload relay setting
—

Relay trip time by class

Cold trip band of each class at the current the relay sees, compared with the starting time and the motor safe stall time.

Tap the chart to see the values.

Approximate curve of the chosen relay

Cold trip time versus multiple of the setting (log scale), with the starting point and the motor limit.

Tap the chart to see the values.

Starter components

Selection rule and minimum value of each component; standard sizes are the most common catalog ratings, confirm with the manufacturer.

Next step

Take this page’s results to another calculator with the fields already filled in.

The calculation report gathers this page's inputs, results, equations, assumptions and references, with fields for project, engineer and revision. The full report also includes the charts and interpretations, in color. In the print dialog, choose Save as PDF.

Method, assumptions and references

Equations used

Relay setting: Ir = FLA (across the line or soft starter); Ir = FLA ÷ √3 ≈ 0.58 FLA (wye-delta, relay in winding leads); limit = 1.25 or 1.15 × FLA (NEC 430.32) or FLA × SF (IEC)
Starting current seen by the relay: across the line k = LRA/FLA; wye-delta k = (LRA/3) ÷ (FLA/√3) = 0.577 LRA/FLA; soft starter k = current limit
Cold trip time: t(k) = Tp(7.2) × ln(k²/(k² − 1.12²)) ÷ ln(7.2²/(7.2² − 1.12²)); Tp(7.2): class 10 = 4 to 10 s, class 20 = 6 to 20 s, class 30 = 9 to 30 s
Conditions: starting time < fastest trip at starting current; slowest trip at locked rotor (k = LRA/FLA) ≤ hot safe stall time
Faults: NEC Table 430.52 dual-element fuse 175%, non-time-delay fuse 300%, inverse-time breaker 250%, instantaneous trip 800% of FLC; IEC aM ≥ FLA, gG ≥ max(1.2 FLA; LRA ÷ k_gG). Contactor AC-3 ≥ FLA (wye-delta: K1 = K2 ≥ 0.58 FLA; K3 ≥ 0.33 FLA). Conductors: ≥ 125% FLC

Assumptions and limits

  • The relay curve is a thermal-model approximation built from the IEC 60947-4-1 limits at 7.2 × setting, from cold. With a hot motor relays trip faster; the manufacturer curve always governs.
  • The IEC gG fuse is estimated from the LRA ÷ rating multiple it withstands for the starting time, read on the manufacturer curve. Standard fuse and contactor sizes are the most common catalog ratings; NEMA sizes by continuous current.
  • Type 1 or type 2 coordination and interrupting rating are not checked: use the manufacturer coordination tables. Frequent starts (more than a few per hour) call for electronic relays or PTC sensors.

Standards and technical documents

  • IEC 60947-4-1:2018: Low-voltage switchgear and controlgear — Contactors and motor-starters — Electromechanical contactors and motor-starters
  • IEC 60269-1 e IEC 60269-2: Low-voltage fuses (gG and aM)
  • IEC 60364-4-43 e IEC 60364-5-52: protection against overcurrent and wiring systems
  • NFPA 70, National Electrical Code 2023, Article 430 (430.6, 430.22, 430.32, Table 430.52)
  • NEMA ICS 2: Industrial Control and Systems — Controllers, Contactors and Overload Relays
  • Schneider Electric. Electrical Installation Guide, chapter N: motors

U.S. regulations

  • NFPA 70 (NEC) Article 430 as adopted by state and local jurisdictions
  • OSHA 29 CFR 1910 Subpart S (electrical) and 1910.147 (lockout/tagout)
  • NFPA 70E: Standard for Electrical Safety in the Workplace
  • UL 60947-4-1: contactors and motor starters

Frequently asked questions

What does this calculator do?

It sets up the protection of a three-phase motor: overload relay setting, trip class, maximum fuse or breaker size under NEC Table 430.52, and starter size. Use it when building a new starter, replacing a motor or chasing nuisance trips at start.

What should the overload relay be set to?

To the nameplate full-load current. In the example, a 40 hp, 460 V motor with 48 A on the nameplate gets the relay at 48 A; NEC 430.32 allows a trip current up to 125% because its service factor is 1.15. On a wye-delta starter the relay sits in the winding leads: set it to 0.58 × 48 = 27.7 A.

How do I choose class 10, 20 or 30?

The class is the maximum cold trip time at 7.2 times the setting: class 10 trips in 4 to 10 s, class 20 in 6 to 20 s and class 30 in 9 to 30 s. The relay must let the start finish and trip before the motor safe stall time. With a 3 s start and a 12 s stall time, class 10 works, tripping between 4.2 and 10.6 s.

What fuse or breaker size does NEC 430.52 allow?

As a percentage of the Table 430.250 full-load current: 175% for dual-element time-delay fuses, 300% for non-time-delay fuses, 250% for inverse-time breakers and 800% for instantaneous-trip breakers, rounded up to the next standard size. For 48 A, a time-delay fuse may be 90 A. If the motor will not start, the exception allows up to 225% for time-delay fuses.

Where do I find starting time and stall time?

The safe stall time is on the motor data sheet, usually 5 to 20 s hot. Starting time can be logged with a recording clamp meter or computed from load inertia in the motor sizing calculator. Small pumps and fans start in 1 to 5 s.

Why does my overload trip during starting?

Common causes: a start too long for the trip class, a setting below nameplate current, low voltage stretching the start, a wye-delta relay installed in the line but set to 58%, or repeated starts with a hot motor. Compare the measured start time with the class band in the chart.

What does the calculator not check?

It does not check short-circuit current rating, type 2 coordination or starts per hour. Use the manufacturer SCCR and coordination tables, and have a qualified engineer review the final design under the NEC as adopted locally.