Shift schedules and crew staffing

Lay out your operation’s schedule and compare the common patterns: how many crews and people, how many hours each works per week, whether every shift is covered and what it costs per month.

Pre-sizing and estimating tool: results do not replace design, calculations or reports signed by a licensed professional, nor verification against the applicable codes and standards.

Pre-sizing

Labor laws and collective bargaining agreements in each country must be evaluated and taken into account; this is the user’s responsibility. The calculator does not check legal limits.

Operation
Schedule
See what was read

Changing the pattern rebuilds the shifts with its typical length (8 or 12 h) from the first shift start; edit them freely afterwards. Changing days on or off switches the pattern to "custom".

Optional: limit and cost
—People needed
—

Schedules compared for the same operation

People needed including reserve (bars) and average hours per person per week (line), with 8- or 12-hour shifts per pattern. The dashed line is the weekly limit entered.

Tap the chart to see the values.

Estimated monthly cost by schedule

Base wage, night premium and hours above the weekly limit, plus payroll burden, for each schedule’s headcount.

Tap the chart to see the values.

Calendar of the chosen schedule (4 weeks)

W = crew working. The last row compares crews on duty with the shifts needed that day.

Next step

Take this page’s results to another calculator with the fields already filled in.

The calculation report gathers this page's inputs, results, equations, assumptions and references, with fields for project, engineer and revision. The full report also includes the charts and interpretations, in color. In the print dialog, choose Save as PDF.

Method, assumptions and references

Equations used

Crews = shifts per day × (operating days ÷ 7) × (cycle days ÷ days worked in the cycle), rounded up
People = crews × positions per shift × (1 + reserve), rounded up
Hours per week = Σ days worked in the week × (shift length − break); average, minimum and maximum over the cycle; hours above the limit summed week by week
Cost per person = [wage + night hours × (wage ÷ hours paid) × premium + hours above limit × (wage ÷ hours paid) × (1 + OT premium)] × (1 + burden)

Assumptions and limits

  • Labor laws and collective bargaining agreements in each country must be evaluated and taken into account; this is the user’s responsibility. The calculator does not check legal limits.
  • Hours above the limit are counted week by week for every crew, with the workweek starting on the weekday that gives the least overtime. Coverage is checked on a simulated calendar with crews staggered evenly over the cycle (or aligned to the week when operation is not continuous). Crews rotate through all shifts, so night hours and shift length are averages of the shifts entered.
  • The comparison uses 8- or 12-hour shifts from the first shift start, with the average break entered. Cost is an estimate for comparing schedules: holiday pay, state daily overtime rules and union agreement terms are not included.

Standards and technical documents

  • Knauth, P. Designing better shift systems. Applied Ergonomics 27(1): 39–44, 1996
  • Health and Safety Executive (UK). Managing shift work: Health and safety guidance, HSG256, 2006
  • International Labour Organization. Night Work Convention, 1990 (No. 171)
  • International Labour Office. Introduction to Work Study, 4th ed., 1992

U.S. regulations

  • Fair Labor Standards Act (29 U.S.C. 201 et seq.) and 29 CFR Part 778: overtime pay above 40 hours per workweek
  • State laws on daily overtime, meal and rest breaks
  • Collective bargaining agreements

Frequently asked questions

What does this calculator do?

It lays out your shift schedule and works out how many crews and people you need, how many hours each person works per week and month, whether every shift is covered and what the schedule costs. It also compares the common patterns (2-2-3, DuPont, continental, 12 on 36 off, 5x2, 6x1, 4x2 and 6 on 2 off) for the same operation.

Does the calculator check whether the schedule is legal?

No. Labor laws and collective bargaining agreements in each country must be evaluated and taken into account; this is the user’s responsibility. The calculator does not check legal limits: the weekly limit field only compares hours against the number you enter.

How is the number of crews calculated?

Crews = shifts per day × (operating days ÷ 7) × (cycle days ÷ days worked). In the example, two 12-hour shifts, 7 days a week, on a 2-2-3: 2 × 1 × 14 ÷ 7 = 4 crews. With 5 positions per shift that is 20 people, and with a 10% reserve, 22.

How do I read the example result?

With 12-hour shifts and a 30-minute unpaid break, each person averages 40.3 hours a week, alternating 34.5 and 46 hours, so the 46-hour weeks carry 6 hours over 40. At $4,000 a month base, 173.3 hours, a 10% night differential, 50% overtime premium and 35% burden, payroll is about $136,000 a month.

Why do 2-2-3 and DuPont need only 4 crews for 24/7?

Because each shift covers 12 hours: two shifts a day and four crews keep the plant running around the clock, each crew working half the days. Eight-hour continental rotations also use 4 crews but each person works more days with shorter shifts. The chart shows people and weekly hours for each pattern side by side.

What is the reserve and how do I pick it?

It is extra staff to cover vacation, absences, leave and training without empty positions. It depends on your PTO policy and absenteeism; use the manpower staffing calculator linked at the bottom of the page to work it out from your own data.

What are the limits of the calculation?

Crews are assumed to rotate through all shifts, so night hours and shift length are averages. Overtime is checked per calendar week of the cycle against the limit you enter; state daily overtime rules, holiday pay and union terms are not included. Validate the schedule with HR, legal counsel and the union before rolling it out.