Home / Machining & welding

Welding cost, filler metal and heat input

Enter the process, joint and length to find how much wire or electrode to buy, how many welder hours and how much gas the job takes, the cost per foot and the heat input of the pass.

Pre-sizing and estimating tool: results do not replace design, calculations or reports signed by a licensed professional, nor verification against the applicable codes and standards.

Pre-sizing
Process

Changing the process loads typical starting values for efficiency, deposition rate, operating factor, electrical settings, gas and prices. Replace them with your WPS, the consumable maker’s data and your suppliers’ prices.

Joint
Costs
—Cost per foot of weld
—

Weld cost breakdown

Total cost of each item for the length entered.

Tap the chart to see the values.

Filler metal versus thickness and joint type

Filler per foot with the same process, root opening, root face, angle and reinforcement as thickness (or fillet leg) changes; for groove welds it compares single-V, double-V and square. Welder hours are proportional and show when you hover the curve. The vertical line is the current size.

Tap the chart to see the values.

Next step

Take this page’s results to another calculator with the fields already filled in.

The calculation report gathers this page's inputs, results, equations, assumptions and references, with fields for project, engineer and revision. The full report also includes the charts and interpretations, in color. In the print dialog, choose Save as PDF.

Method, assumptions and references

Equations used

Area: fillet A = z²/2 + ⅔ · z√2 · h; single-V A = t·g + (t − c)² · tan(α/2) + ⅔ · w · h; double-V A = t·g + 2 · [(t − c)/2]² · tan(α/2) + 2 · ⅔ · w · h; square A = t·g + ⅔ · w · h; w = top opening + 3 mm (1/8 in)
Deposited metal (kg/m) = A (mm²) · 7,850 · 10⁻⁶ (lb/ft = kg/m · 0.672); filler = deposited ÷ deposition efficiency
Arc time = total deposited metal ÷ deposition rate; welder hours = arc time ÷ operating factor; gas = flow · arc time
Energy (kWh) = U · I · arc time ÷ (1000 · power source efficiency); heat input Q = k · U · I · 60 ÷ (1000 · v) [kJ/mm; v in mm/min] (kJ/in = kJ/mm · 25.4)

Assumptions and limits

  • Geometric cross-section with parabolic reinforcement (⅔ of width × height) extending 1/16 in past each edge; root penetration, back-gouging and back-welding, and misalignment are not included. Steel density: 490 lb/ft³ (7,850 kg/m³).
  • Efficiency, deposition rate, operating factor and prices in the list are typical starting values for carbon steel; WPS data, the consumable maker’s charts and your shop’s time records prevail.
  • Heat input is for one pass at the electrical settings entered; it does not replace procedure qualification or preheat assessment.

Standards and technical documents

  • AWS D1.1/D1.1M:2020 Structural Welding Code — Steel
  • EN 1011-1:2009 Welding — Recommendations for welding of metallic materials — Part 1: General guidance for arc welding
  • ISO/TR 17671-1:2002 Welding — Recommendations for welding of metallic materials — Part 1: General guidance for arc welding
  • Lincoln Electric. The Procedure Handbook of Arc Welding, 14th ed., 2000 (deposition rates, efficiencies and weld cost)
  • ISO 2553:2019 Welding and allied processes — Symbolic representation on drawings — Welded joints
  • Marques, P. V.; Modenesi, P. J.; Bracarense, A. Q. Soldagem: Fundamentos e Tecnologia, 4ª ed., Elsevier, 2017

U.S. regulations

  • OSHA 29 CFR 1910 Subpart Q: Welding, Cutting and Brazing (1910.251 to 1910.255)
  • ANSI Z49.1: Safety in Welding, Cutting, and Allied Processes

Frequently asked questions

What does this calculator do?

It estimates how much wire or electrode to buy, how many welder hours and how much gas a welding job takes, the cost per foot and the heat input of the pass. It starts from the joint geometry (fillet, single-V, double-V or square) to get the weld cross-section and deposited metal, then uses typical deposition efficiency and rate for each process. Use it to quote, buy filler metal and compare processes.

What is deposition efficiency?

It is the share of the filler metal bought that ends up in the weld. With stick electrodes you lose the stub, the coating turns into slag and there is spatter, so only 55% to 65% of the weight stays in the joint; solid-wire MIG/MAG tops 90%. In the example, 0.58 lb/ft of deposited metal needs 0.61 lb/ft of wire at 95% efficiency.

How do I read the example result?

The example is a 60° single-V groove in 1/2 in plate welded with MIG/MAG: the weld section is 0.17 in², or 0.58 lb of metal per foot. For 150 ft of weld it takes 91.5 lb of wire, 11.3 h of arc time and 25.1 welder hours (at a 45% operating factor), 361 ft³ of gas and 83 kWh. Total cost is $1,709, or $11.40 per foot, and labor is about four fifths of it.

What is operating factor and why does it matter so much?

It is the share of the welder’s paid time with the arc on. The rest goes to tacking, cleaning, grinding, changing electrodes and positioning the part. At 45%, the welder welds only 27 minutes an hour, which is why labor dominates weld cost. Measuring the real factor on the shop floor usually corrects an estimate more than any other input.

How is heat input calculated?

With the EN 1011-1 / ISO/TR 17671-1 formula: Q = k · U · I · 60 ÷ (1000 · v), with volts, amps and travel speed in mm/min, where k is the process thermal efficiency (0.8 for MIG/MAG, stick and flux-cored, 0.6 for TIG, 1.0 for submerged arc). In the example, 26 V, 240 A and 12 in/min give 25.0 kJ/in. AWS D1.1 uses arc energy without k (31.2 kJ/in here); the allowed range comes from your qualified WPS.

What are the limits of the calculation?

The weld section is geometric: root penetration, back-gouging and back-welding, misalignment and gaps beyond the drawing are not included and usually raise consumption. Efficiency, deposition rate and operating factor are typical starting values. The calculation does not replace procedure or welder qualification under AWS D1.1, nor does it assess preheat.

How many pounds of electrode per foot of weld?

It depends on weld size and process. For the example joint (60° V in 1/2 in plate, 0.58 lb/ft of deposited metal), stick electrode at about 60% efficiency would need roughly 0.96 lb of electrode per foot, against 0.61 lb/ft of MIG/MAG wire. Pick the process in the list to see the figure with each one’s typical settings.