Paste the cell’s elements with manual, automatic and walking times to see whether each operator closes the cycle within takt, where they wait for a machine and how many operators are needed.
Pre-sizing and estimating tool: results do not replace design, calculations or reports signed by a licensed professional, nor verification against the applicable codes and standards.
One chart per operator: elements in order, time in seconds and the red takt line.
Manual, walking and machine wait stacked; the line is takt.
Take this page’s results to another calculator with the fields already filled in.
The calculation report gathers this page's inputs, results, equations, assumptions and references, with fields for project, engineer and revision. The full report also includes the charts and interpretations, in color. In the print dialog, choose Save as PDF.
It is the form that shows, for each operator, the manual time of each element, the time each machine runs on its own and walking, drawn against the takt line. It comes from the Toyota Production System and is used to decide how many machines one operator tends and in what order.
The cycle is the larger of two values: the operator’s manual plus walking time and, for each machine, its manual plus automatic time. If the machine is not done when the operator returns, they wait. In the example operator 1 has 35 s of work, but the lathe takes 9 + 38 = 47 s: the cycle is 47 s with 12 s of waiting.
With 500 parts in 450 min per shift, takt is 54 s. Work content (manual plus walking) is 75 s, so at least 2 operators are needed. The automatic split gives operator 1 elements 1 to 4 (47 s cycle) and operator 2 elements 5 to 9 (45 s, with 5 s waiting for the washer). Both meet takt.
Time each element at the station several times and use the lowest repeatable time (as in Toyota standardized work) or the standard time from a time study. Automatic time comes from the machine display (machine cycle after start). Walking can be measured or estimated at roughly 1 s per meter (about 3 ft) at a normal pace.
Waiting shows the machine is slower than the operator’s work. Options: give them another element to do during the wait, cut the automatic time (feeds, tool paths) or change the order so they reach the machine later. Large waits for every operator suggest the work can be combined into fewer people.
It keeps element order and finds the split into consecutive blocks with the shortest maximum cycle, which is optimal under that rule. In practice layout, safety, skills and the walk back change what is feasible; treat the result as a good starting point and confirm it at the station.
It assumes fixed times (no variation), one part per cycle, the walk on each operator’s last line as the return to the start and each machine used by one operator only. Fatigue and allowances are not included: add them to manual time if you wish. For ergonomics of repetitive tasks, follow OSHA and NIOSH guidance.
Important notice: Indus Metrics tools produce estimates and pre-sizing results from the data you enter and from published engineering methods. They do not replace design, calculations or reports signed by a licensed professional engineer (PE), nor verification against the applicable codes, standards and regulations, such as OSHA rules and the ASME codes. Material and fuel properties vary: check manufacturer data or your own process analyses before deciding. By using this site you agree to the Terms of Use.