Several molders, presses or looms for the same jobs, or a job shop where each job has its own routing? See which rule delivers on time, how each machine is loaded, and print a dispatch list for each one.
Pre-sizing and estimating tool: results do not replace design, calculations or reports signed by a licensed professional, nor verification against the applicable codes and standards.
Click a row to see the Gantt chart and dispatch list for that rule. ✓ marks the best value in each column.
Dispatch rules give a good schedule that is quick and easy to explain on the shop floor, but not necessarily the optimum: with several machines and routings the exact optimum needs mathematical programming. Always check with the people who know the machines.
Run, setup and idle time of each machine, from the start to the end of the schedule.
Take this page’s results to another calculator with the fields already filled in.
The calculation report gathers this page's inputs, results, equations, assumptions and references, with fields for project, engineer and revision. The full report also includes the charts and interpretations, in color. In the print dialog, choose Save as PDF.
Use it when more than one machine is involved: several machines doing the same work (injection molders, presses, looms) where you must decide which one takes each job, or a job shop where each job visits different machines in different orders (saw, lathe, mill, drill). For one machine or the bottleneck, the job sequencing calculator is simpler and shows the family setup rules in detail.
Standard time = job quantity × time per part (time study or routing) ÷ actual efficiency. Full setup is the measured changeover from one family to another; the short one is the adjustment when the family is already set up. Relative speed comes from each machine’s actual hourly output on the same product. Allowed machines come from the mold, tooling or part size.
There are 9 jobs on 3 injection molders, one of them 20% slower and free only at 9:00. The order entered finishes at 22.50 h with 3.50 h of tardiness on one job. EDD (earliest due date first) delivers every job on time and finishes at 26.00 h. LPT finishes first (21.50 h) but makes 4 jobs late: it balances the load, it does not protect due dates.
There are 6 jobs going through saw, lathe, mill and drill. The mill is the bottleneck with 14.50 h of load: no schedule can finish earlier. MWKR reaches exactly 14.50 h (the optimum) but makes two jobs late; EDD finishes at 16.00 h with only 1.00 h of tardiness on one job. The wait table shows where each part queued and behind which job.
It is the common-sense shop floor rule: a free machine with a part waiting starts work right away. When several parts are queued, the chosen rule decides which goes in (SPT, EDD, CR, MWKR or the order entered). It is the simplified Giffler–Thompson method used in scheduling systems; it gives good schedules but does not guarantee the optimum.
Not necessarily. Scheduling several machines is a hard problem: the number of combinations grows very fast and the exact optimum needs mathematical programming. The rules on this page give a good arrangement in seconds that is easy to explain. The lower bound shows how much could still be gained: if the rule reaches it, the schedule is optimal for makespan.
All jobs are released at the start, with no breakdowns, no material shortages and no splitting a job across machines. With parallel machines, setup depends only on the previous family; in routings, each operation’s setup is fixed. The calendar is the same for every machine, without weekends or holidays, and there is no operator limit. For hundreds of jobs with labor or tooling constraints, use a scheduling (APS) system.
Important notice: Indus Metrics tools produce estimates and pre-sizing results from the data you enter and from published engineering methods. They do not replace design, calculations or reports signed by a licensed professional engineer (PE), nor verification against the applicable codes, standards and regulations, such as OSHA rules and the ASME codes. Material and fuel properties vary: check manufacturer data or your own process analyses before deciding. By using this site you agree to the Terms of Use.